12/21/2019 Saturday Meeting developing the master plan

  • Immediately After Kickoff
  • WEEK 1
    • Prototyping - Design and Build
    • Practice Field
      • Continue to make (cardboard)
      • Drive Team Practice
    • Deep Dive into Game Play
    • Procurement - (Purchasing)
      • Lists from each team
    • Award Decisions - Rough Draft
    • Drive Train initial Design
    • Mock Matches
    • NEEDS
      • Mentors for scouting all that week
      • Receiving Department
      • Who is trained on equipment
      • Drive practice during day and after hours
      • Feed for Drive Team
      • Test for Drive Team
  • WEEK 2
    • 1/2 Chassis complete
    • Drive Train Finalized
    • Decent amount of Subsystem Testing
    • Mock Matches Continue and Review
    • Tracking Receipts
  • WEEK 3
    • DriveTeam Tryouts
    • Chassis Done